Context
- Source: PIB
- India is accelerating Pumped Storage Projects (PSPs) to support its clean energy transition.
- The Central Electricity Authority (CEA) has identified 345.38 GW of potential across 320 projects and projects substantial capacity expansion by 2035–36.
What is Pumped Storage Hydropower?
- Pumped Storage Hydropower (PSH) is a large-scale, long-duration energy storage technology that uses water and gravity to store surplus electricity and generate power during high demand.
Working Mechanism
- Storage phase: Surplus electricity, especially from solar and wind, pumps water from a lower reservoir to an upper reservoir, storing energy as gravitational potential energy.
- Generation phase: During peak demand or low renewable generation, stored water flows back through turbines to generate electricity.
- Recycling: Water is repeatedly circulated between the two reservoirs, enabling multiple storage and generation cycles.
Role in Renewable Energy
- PSPs address the intermittency of solar and wind energy by storing surplus electricity and supplying it during low renewable generation.
Types of Energy Storage
- Battery Energy Storage Systems (BESS): Provide rapid-response, short-duration storage; support frequency regulation, peak demand management and grid balancing; can be deployed quickly near generation or consumption centres.
- Pumped Storage Projects (PSPs): Offer long-duration storage, high capacity and long operational life; require suitable geography and longer development timelines.
Types of Pumped Storage Projects
- On-stream PSP: Both reservoirs are located on a river, stream or nallah.
- Off-stream open-loop PSP: One reservoir is on a natural watercourse; the other is away from rivers or perennial streams.
- Off-stream closed-loop PSP: Both reservoirs are away from perennial natural watercourses.
- Environmental significance: Off-stream PSPs are increasingly explored for faster execution and potentially lower impacts on aquatic ecology, subject to site-specific conditions.
Status and Potential in India
- Operational capacity: 7.43 GW across 10 PSPs as of August 2026.
- Under construction/implementation: 15.87 GW across 11 projects.
- Concurred/appraised by CEA: 10.40 GW across 8 projects.
- National potential: 345.38 GW across 320 PSPs.
- On-stream: 56.67 GW from 62 projects.
- Off-stream: 288.71 GW from 258 projects.
- Regional distribution: Western Region leads with 129.72 GW, followed by Southern 97.76 GW, Eastern 53.41 GW, Northern 50.32 GW and North Eastern 14.18 GW.
- State-level leader: Maharashtra has the highest identified potential at 67.36 GW.
- Energy storage requirement: CEA projects 73.93 GW by 2031–32, including 26.69 GW from PSPs and 47.24 GW from BESS.
- Projected expansion: CEA envisages 100.81 GW of PSP additions during 2025–26 to 2035–36, raising cumulative capacity to about 105.56 GW.
- Global position: IRENA reports global pumped storage capacity at 159.8 GW at end-2025, led by China 66 GW, Japan 22 GW and the US 19 GW. India ranked fourth globally with 7.18 GW.
Key Government Initiatives
- PSP Development Guidelines, April 2023: Notified by the Ministry of Power to facilitate faster project development.
- Infrastructure support: Budgetary support for roads, bridges, railway sidings, ropeways, communication facilities and transmission lines.
- Competitive procurement: Tariff-Based Competitive Bidding Guidelines, 2025 provide a transparent framework for procuring PSP storage capacity and stored energy.
- Transmission charge waiver: PSPs awarded for construction by 30 June 2028 are eligible for 100% ISTS charge waiver for 25 years from commercial operation.
- Faster approvals: Revised CEA guidelines reduced DPR concurrence timelines from 90 to 50 days and removed inter-state clearance requirements.
- Environmental clearances: MoEFCC introduced Category B2 classification for eligible PSPs and reduced baseline data requirements for off-stream projects, with revised forest survey and borehole exploration provisions.
- Integrated grid planning: National electricity planning integrates energy storage and transmission infrastructure for renewable integration, reduced congestion and reliability.
- Digital monitoring: CEA’s Jal Vidyut DPR portal enables real-time monitoring of surveys and investigations.
- CEA concurrence exemption: In August 2025, the capital expenditure threshold for CEA concurrence was revised to ₹3,000 crore, while off-stream closed-loop PSPs were exempted irrespective of project cost.
Significance for India
- Supports India’s target of 500 GW non-fossil fuel capacity by 2030.
- Provides long-duration storage to complement short-duration BESS.
- Improves grid stability, peak management and renewable energy integration.
- Strengthens energy security and grid resilience.
- Promotes regional infrastructure and hydropower development.
Challenges and Way Forward
- Geographic suitability and long gestation periods.
- Environmental and forest clearances, aquatic ecology concerns.
- Need for integrated transmission and storage planning.
- Balanced development of on-stream and off-stream projects with community and ecological safeguards.
Constitutional and Legal Context
- The Electricity Act, 2003 governs generation, transmission, distribution and regulatory oversight.
- The Central Electricity Authority (CEA) is the statutory technical planning and appraisal body.
- Environmental clearance for eligible projects is linked to MoEFCC notifications, including Category B2 provisions.
Mains Practice Question
Pumped Storage Hydropower can play a crucial role in addressing the intermittency of renewable energy in India. Discuss.